The Dunham Road contractor’s asphalt and striping work has been substantially delayed due to the weather. The remaining work will be completed as weather permits. The current schedule calls for the asphalt work to be completed by Monday July 5, 2021 and the striping to be placed immediately following on Tuesday July 6, 2021, weather permitting. The restoration of normal traffic flow is anticipated to take place on Wednesday July 7, 2021. This date remains weather dependent. Traffic will continue to be restricted to southbound only until the project is completed in order to provide for the safety of all.